Continuous strip footings for foundations, garages, and additions: total run length and the footing cross-section in, cubic yards out. Decimals welcome throughout.

Concrete needed
1.65 cu yd

Order 1.81 cu yd with 10% waste  |  in bags: 75 × 80 lb (footings this size are usually a ready-mix call)

Common footing sections, per 10 ft of run

Section (W × D)Typical wall aboveCu yd per 10 ft
12" × 6"4" wall / light0.19
16" × 8"8" foundation wall0.33
20" × 10"10" wall / 2-story0.51
24" × 12"Heavy / engineered0.74

Measure run length along the footing centerline so corners aren't double-counted. Trench pours into irregular soil often run 10–20% over the math — order accordingly.

Common questions

How much concrete do I need for footings?

Total footing length × width × depth (converted to feet) ÷ 27. A typical 50-foot run of 16" × 8" footing needs about 1.65 cubic yards — the calculator handles any run and section size, and footings are nearly always a ready-mix order, not bags.

How wide and deep should footings be?

The rule of thumb: footing width = 2× the wall thickness (so 16" under an 8" wall) and depth equal to the wall thickness, minimum 8". Soil bearing capacity and your local code make the final call — soft soils need wider footings.

How deep do footings need to be in the ground?

The bottom of the footing must sit below the frost line on undisturbed soil — anywhere from 12" in the South to 48"+ in northern states. This is the most commonly enforced inspection item in foundation work.

Do footings need rebar?

Standard practice (and most codes) call for at least two continuous runs of #4 rebar, lapped 20"+ at splices and corners, held 3" off the soil on chairs. Add vertical dowels if a poured or block wall goes on top.