FigureThePour

Rebar Calculator for Slabs

Slab size in, shopping list out: bars each direction, total linear feet with 5% for laps, and how many 20-foot sticks to put on the truck.

Rebar needed
614 linear ft (incl. 5% laps)

Grid: 15 bars lengthwise × 15 bars widthwise  |  buy 31 × 20 ft sticks

Which bar size?

BarDiameterTypical use
#33/8"Patios, walkways, light slabs
#41/2"Driveways, garage slabs, footings — the residential default
#55/8"Heavy equipment pads, engineered work

Assumes 3" edge cover and bars at mid-slab height on chairs. Add tie wire (one tie per intersection: rows × cols) and chairs every 3–4 ft along bars.

Common questions

What rebar spacing should I use for a slab?

Residential slabs typically use #3 or #4 rebar on a 16 or 18 inch grid. Driveways and garage slabs lean 12–16", light-duty patios 18–24". Local code and soil conditions govern — when in doubt, tighter spacing and #4 bar.

How much does rebar overlap at splices?

Lap splices should overlap at least 40 bar diameters — about 20 inches for #4 (½") bar. The calculator adds 5% to total length to cover laps and cut waste.

Rebar or wire mesh for a slab?

Mesh (6x6 W1.4) is fine for 4" slabs with foot traffic. Anything carrying vehicles, point loads, or on questionable soil benefits from a rebar grid — it holds position better during the pour and adds real flexural strength.

How far from the edge does rebar start?

Keep 3 inches of concrete cover from every edge, and support bars on chairs at mid-slab height — rebar lying on the gravel does nothing.